Determine the equivalent annual annuity for the following project if the appropriate discount rate is 15%.
Initial Outlay = $1,200
Cash Flow Yr 1 = $800
Cash Flow Yr 2 = $500
Cash Flow Yr 3 = $700
a) $50
b) $146
c) $674
d) $431