1. A new entrance road to the pump station will be constructedusing crushed stone. The road is 675’ long, 27’ wide, and 18â€thick. The road will be constructed using a dozer andself-propelled tamping foot roller. The dozer has a power-shittransmission and a rated blade capacity of 6 LCY and pushing adistance of 100 feet per cycle. Maximum reverse speed is 4 MPH. Itwill spread the rock in 6†lifts. The compactor will follow eachspreading lift with 3 passes. The compactor width is 6 feet andspeed per pass is 1.5 MPH. Job efficiency is assumed to be 50minutes per hour for both operations. ï‚· How much crushed stone(rock) is required? (LCY) ï‚· How long will it take to spread therock? (Hours) ï‚· How long should it take to compact therock?(Hours)