1. A precedence diagram is shown below. Solve the network forthe basic scheduling information. For each activity, show thecomputed value of early start, early finish, late start, latefinish, total float, and free float.
?
Activity | Duration |
mobilize | 1 |
remove siding | 4 |
excavate/form slab | 7 |
place slab | 4 |
set support beam | 1 |
stud wall up | 6 |
install siding | 4 |
install windows | 5 |
set raffers | 4 |
install roof | 6 |
finish trim | 4 |
paint siding | 7 |
move out | 1 |