1. Mocha Company manufactures a single product by a continuous process, involving three production departments....
80.2K
Verified Solution
Link Copied!
Question
Accounting
1. Mocha Company manufactures a single product by a continuous process, involving three production departments. The records indicate that direct materials, direct labor, and applied factory overhead for Department 1 were $100,000, $125,000, and $150,000, respectively. The records further indicate that direct materials, direct labor, and applied factory overhead for Department 2 were $55,000, $65,000, and $80,000, respectively. In addition, work in process at the beginning of the period for Department 1 totaled $75,000, and work in process at the end of the period totaled $60,000.
The journal entry to record the flow of costs into Department 1 during the period for direct materials is
a.
Materials 55,000
Work in ProcessDepartment 1 55,000
b.
Work in ProcessDepartment 1 55,000
Materials55,000
c.
Materials 100,000
Work in ProcessDepartment 1 100,000
d.
Work in ProcessDepartment 1 100,000
Materials100,000
2. The following production data were taken from the records of the Finishing Department for June:
Inventory in process, June 1 (35% completed)
4,900
units
Completed units during June
64,700
units
Ending inventory (56% complete)
3,400
units
The number of materials equivalent units of production in the June 30 Finishing Department inventory, assuming that the first-in, first-out method is used to cost inventories and materials were added at the beginning of the process, is
a. 63,200 units
b. 68,100 units
c. 3,400 units
d. 59,800 units
3. Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools. The budgeted activity cost and activity base data by product are provided below.
Activity Cost
Activity Base
Procurement
$393,300
Number of purchase orders
Scheduling
232,500
Number of production orders
Materials handling
494,000
Number of moves
Product development
739,300
Number of engineering changes
Production
1,487,300
Machine hours
Number ofPurchaseOrders
Number ofProductionOrders
NumberofMoves
Number ofEngineeringChanges
MachineHours
NumberofUnits
Disk drives
4,110
350
1,290
12
2,300
1,800
Tape drives
2,400
175
780
4
9,900
4,300
Wire drives
11,500
800
4,400
22
10,600
2,000
The activity rate for the scheduling activity cost pool is
a.$296.83 per production order
b.$175.47 per production order
c.$21.84 per production order
d.$65.23 per production order
Answer & Explanation
Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!