13.7 Table EX 13.7 shows the precedence
relationships among the activities to complete a project.
Table EX...
50.1K
Verified Solution
Link Copied!
Question
Advance Math
13.7 Table EX 13.7 shows the precedencerelationships among the activities to complete a project.
Table EX 13.7
Activity
Predecessor
Duration (Weeks)
A
–
6
B
–
2
C
A
4
D
B
5
E
B
2
F
C, D
4
G
C, D
7
H
E, G
5
I
F
4
Construct an activity on node network for the project.
Identify the paths and path project durations.
Determine the critical path and the expected project completiontime.
Find the ES, LS, EF, LF, and slack time for each activity.
Answer & Explanation
Solved by verified expert
3.7 Ratings (660 Votes)
Construct an activity on node network for theprojectIdentify the paths and path projectdurationsPathDurationWeeksACGH6475 22ACFI6444 18BDFI2544 15BEH225 9BDGH2575 19Determine the critical path and the expected projectcompletion timeCritical path is the longest path and here the critical path isACGH with duration 22 weeksExpected project completion time is duration of critical path 22 weeksFind the ES LS EF LF and slack time for
See Answer
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!