21) The Mega Construction Company recently switched to activity-based costing (ABC) from the...
90.2K
Verified Solution
Link Copied!
Question
Accounting
21)
The Mega Construction Company recently switched to activity-based costing (ABC) from the department allocation method. The department method allocated overhead costs at a rate of $60 per machine hour. The cost accountant for the Finishing Department has gathered the following data:
Activity Cost Drivers Rate
Material handling Tons of material handled $80
Machine setups Number of production runs 3,750
Utilities Machine hours 25
Quality control Number of inspections $500
During April, Mega purchased and used $100,000 of direct materials at $20 per ton. There were 8 production runs using a total of 12,000 machine hours in April. The manager of the Finishing Department needed 12 inspections. Actual overhead costs totaled $820,000 for the month.
How much overhead costs were applied to the Work-in-Process Inventory during April using activity-based costing?
Answer & Explanation
Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!