27. In the pull approach
A. subassembly parts are manufactured and stored just in case they are needed later in the manufacturing process.
B. Finished goods are completed and stored just in case unexpected and rush customer orders are received.
C. the manufacturing process begins with a customer placing an order.
D. None of the above.
Answer & Explanation
Solved by verified expert