Question
Accounting
A firm is planning to take a project that if funded entirely with equity has net after tax cash flows as indicated in the table below.
Year
Cash flow
0
-13000000
1
1500000
2
1500000
3
1500000
4
1500000
5
1500000
6
2000000
7
2000000
8
2000000
9
2000000
10
2000000
11
2500000
12
2500000
13
2500000
14
2500000
15
2500000
16
3000000
17
3000000
18
3000000
19
3000000
20
6000000
The firm estimates that the asset beta (i.e., when funded entirely with equity) for comparable projects is 1.2. The risk free interest rate is 4.0% and the firm expects the market return over the next 20 years to average 12.0%. The project will operate as a corporation with a combined federal and state income tax rate of 26%.
The firm plans to fund 15% of the project with debt that pays 4.0% interest annually for 20 years at which time the entire principal is due.
For all of the following, use annual cash flows and annual interest payments.
1a. Using the capital asset pricing model, determine the required return of the project if funded entirely with equity.
b. Calculate the net present value of the project if funded entirely with equity.
2a. Find the leveraged equity beta.
b. Calculate the required return on leveraged equity. (You may use the capital asset pricing model or calculate the return directly using the debt equity ratio, the return on unleveraged equity and the interest rate.)
c. Determine the weighted average cost of capital.
d. Using the WACC method, what is the net present value of the leveraged project?
3a. Calculate the amount of the each annual interest payment on the loan.
b. Calculate the present value of the interest payments.
c. Determine the value of the tax shield of interest.
d. Using the APV method, what is the net present value of the leveraged project?
4a. Determine the initial investment by equity in the project and the annual cash flows to equity for the project in years 1-20.
b. Using the FTE method, what is the net present value of the leveraged project?
Answer & Explanation
Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!