A firm uses graphical techniques in its aggregate planningefforts. Over the next twelve months (its intermediate period), itestimates the sum of demands to be 80,000 units. The firm has 250production days per year. In January, which has 20 production days,demand is estimated to be 8,000 units. Which of the following iscorrect?
- A. the firm must hire workers between December and January
- B. level production of 320 units per day is below the Januaryrequirement
- C. the January requirement is below level production of 400units
- D. level production is approximately 400 units per day
- E. level production is approximately 500 units per day