A hydro power station is required to deliver 48MW ofpower to the national grid from a site where the available head is16m The alternator efficiency may be taken as 96%.The proposedrotational speed of the coupled turbo-alternators is 150r/min andthe specific speed of the available turbines is 400. Estimate thenumber 9f units required