A job was budgeted to require 3 hours of labor per unit at $8.00 per...
80.2K
Verified Solution
Link Copied!
Question
Accounting
A job was budgeted to require 3 hours of labor per unit at $8.00 per hour. The job consisted of 7,100 units and was completed in 19,300 hours at a total labor cost of $172,800. What is the total direct labor variance?
Multiple Choice
$800 unfavorable.
$7,100 unfavorable.
$2,400 unfavorable.
$2,513 unfavorable.
$4,913 unfavorable.
Answer & Explanation