A private equity firm is considering five competing projects in which to invest in the upcoming quarter. The firm needs to decide how to allocate its available capital based upon the combination of projects(denoted as a to e)selected to maximize returns(based upon net present value(npv)).Table 1 below presents the capital requirements and the NPV for each project, along with the associated risk(given as a percentage of the initial investment).The company has $43 million in capital to allocate, with the goal of having an average associated risk of no more than 5%.There are some additional constraints to be met: i) if project B is selected, then project e is also selected;ii) if either project a is selected or project c selected, but not both; iii) at least one of projects a,b,d, is selected.

Table 1. project data

project

Npv(M$)

Risk(%)

Capital(M$)

a

19

4

14

b

22

5

10

c

24

6

12

d

27

7

15

e

21

5

13

make linear programing

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students