A project consists of 10 activities whose precedence relationships and their estimates are shown below:
Activity: A B C D E F G H I J
Predecessor: - - - - B E C A, F E D, G
Duration: 6 10 11 9 5 8 2 8 7 4
1Find the critical path for the project.
2What is the corresponding project completion time?