Accounting
ABC Construction, Inc's current project has a contract value of $1,109,655. Actual costs to date are $711,685 and total billed to customer is currently $675,000. Estimated cost at completion is $898,820. If project is overbilled or underbilled, by how much? Overbilled by 166,981.32 Underbilled by 166,981.32 Overbilled by 203,666.32 Underbilled by 203,666.32 Due to missing information, determination is not possible. Project is neither underbilled or overbilled. Billing is exactly as it should be
Answer & Explanation
Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!