Hawkflight construction utilizes the percentage of completion method to determine profit on construction contracts. The percentage of completion is determined by referring to the proportion that contract costs incurred to date bear to the estimated total contract costs.
Included in the material purchased are the following amounts which were shown as inventories on hand at year end:
$
Contract A 2 000
Contract B 5 000
Contract C 5 000
The hired equipment was used as follows on the following contracts:
Contract A 35%
Contract C 65%
Design and technical assistance as well as insurance must be allowed between the different contracts on the basis of estimated total costs.
Payments to subcontractors include the following prepayments:
Contract A $20 000
Contract C 5 000
Answer & Explanation
Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!