activity
follows
optimistic duration
most likely direction
pessimistic duration
A
-
4
6
14
B
A,C
3
4
5
C
-
3
5
13
D
A,E
12
18
24
E
-
8
10
18
F
A,E
4
6
8
G
B,F
7
8
9
H
G
10
12
14
I
G
5
6
7
J
D,I
5
7
9
Calculate the probability of completing the project between 35
and 40 weeks?...
90.2K
Verified Solution
Link Copied!
Question
General Management
activity
follows
optimistic duration
most likely direction
pessimistic duration
A
-
4
6
14
B
A,C
3
4
5
C
-
3
5
13
D
A,E
12
18
24
E
-
8
10
18
F
A,E
4
6
8
G
B,F
7
8
9
H
G
10
12
14
I
G
5
6
7
J
D,I
5
7
9
Calculate the probability of completing the project between 35and 40 weeks? [4 pts]
f Answer the project manager’s question: “I want to tell the clientthat there is a 10.03% chance the project will take longer than Xweeks - what figure should I give them (i.e. find X)?”[4]
Answer & Explanation
Solved by verified expert
3.8 Ratings (541 Votes)
We need to calcuate the project duration using the critical pathmethod PERT The expected duration isE optimistic 4most likely
See Answer
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!