Activity
Predecessor
Optimistic
Most Likely
Pessimistic
A
4
7
10
B
2
9
10
C
A,B
2
5
8
D
C
16
19
28
E
C
6
9
24
F
E
1
7
13
G
C
4
10
28
H
D,F
2
5
14
I
G,F
5
8
17
J
H,I
2
5
8
Determine the expected completion
time for each activity.
Construct the AON network for the
activities of this...
60.1K
Verified Solution
Link Copied!
Question
General Management
Activity
Predecessor
Optimistic
Most Likely
Pessimistic
A
4
7
10
B
2
9
10
C
A,B
2
5
8
D
C
16
19
28
E
C
6
9
24
F
E
1
7
13
G
C
4
10
28
H
D,F
2
5
14
I
G,F
5
8
17
J
H,I
2
5
8
Determine the expected completiontime for each activity.
Construct the AON network for theactivities of this contract and determine the critical path for theproject.
Answer & Explanation
Solved by verified expert
3.9 Ratings (461 Votes)
Expected time of each activityActivitytotmtpteto4tmtp62tpto62A471071B29108178C25851D161928204E6924119F171374G410281216H251464I5181715674J25851The earliest and latest expected time for each activity iscalculated by considering the expected time teActivityImmediate
See Answer
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Zin AI - Your personal assistant for all your inquiries!