Albert Construction Company had a contract starting April 2018, to construct a $42,000,000 building that...
90.2K
Verified Solution
Link Copied!
Question
Accounting
Albert Construction Company had a contract starting April 2018, to construct a $42,000,000 building that is expected to be completed September 2019, at an estimated cost of 38,500,000. At the end of 2018, the cost to date were $17,710,000 and the estimated cost to complete had not changed. The progress billings during 2018 were $8,400,000 and the cash collected during 2018 was $5,600,000/ Albert uses the percentage-of-completion method.
At December 31, 2018, Albert would report Construction in Process in the amount of ?
a) 19,320,000
b) 17,710,000
c) 16,520,000
d) 1,610,000
Answer & Explanation
Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!