An all-equity firm is considering the projects shown below. The T-bill rate is 4% and the expected market return is 14%. Using the CAPM, calculate the risk adjusted required return for each project. If the firm uses its current WACC of 12 percent to evaluate these projects, which project(s), if any, will be incorrectly rejected? Which project(s), if any, will be incorrectly accepted?
Project Expected Return Project Beta
A 10.0% 0.5
B 19.0% 1.2
C 13.0% 1.4
D 20.0% 2.5
CAPM: E(Ri) = RF + [Bi X (E(Rm) Rf)]
Where; E(Ri) = expected return for project i.
RF = risk-free rate (T-bill rate)
Bi = Beta for project i.
E(Rm) = expected return for the market
Answer & Explanation
Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!