Assume that $102,000 is budgeted for fixed overhead. $95,000 was actually spent on fixed overhead....
70.2K
Verified Solution
Link Copied!
Question
Accounting
Assume that $102,000 is budgeted for fixed overhead. $95,000 was actually spent on fixed overhead. Fixed overhead is applied to production at $10 per labor hour, and the achieved output was 5,000 units. The standard labor hours are 2 hours per unit.
The total fixed overhead variance is $2,000 favorable.
All of these choices are correct.
The fixed overhead spending variance is $7,000 favorable.
The fixed overhead volume variance is $5,000 unfavorable.
Answer & Explanation
Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!