At the End of | Stage | Estimated Cost | Cumulative Estimate | Estimated Duration | Stage Completed (Stage 1) | Stage Completed (Stage 2) | Stage Completed (Stage 3) | Stage Completed (Stage 4) | Stage Completed (Stage 5) | Actual Cost of Stage to Date | Actual Cost of Project to Date |
Month 1 | Stage 1 | $6,500 | | 1 Month | 100% | Not Yet | Not Yet | Not Yet | Not Yet | $6,450 | |
Month 2 | Stage 2 | $2,500 | | 1 Month | 100% | 100% | Not Yet | Not Yet | Not Yet | $2,500 | |
Month 3 | Stage 3 | $2,500 | | 1 Month | 100% | 100% | 60% | Not Yet | Not Yet | $2,800 | |
Month 4 | Stage 4 | $3,000 | | 1 Month | 100% | 100% | 100% | 30% | Not Yet | $3,200 | |
Month 5 | Stage 5 | $1,500 | | 1 Month | 100% | 100% | 100% | 30% | Not Yet | | |
1. what can you do if you find your progress of project development doesn't meet the expectations?
2. please calculate PV, EV, AC, CV, CPI, SV, SPI. BAC, ETC, and EAC at Stage 5
3. How much money will you save/ overspend comparing to your budget?
Answer & Explanation
Solved by verified expert