Balance the assembly line shown below for (a) a shift output of 30 pieces and...
80.2K
Verified Solution
Link Copied!
Question
Accounting
Balance the assembly line shown below for (a) a shift output of 30 pieces and (b) a shift output of 24 pieces. Assume an 6-hour shift, and use the rule: choose the assignable task with the longest processing time. Compute the line efficiency for each case.
Fill in the table below for a shift output of 30 pieces. Break ties by choosing the lowest task number. If your answer is zero, enter "0". Round your answers to the nearest whole number.
Workstation
Tasks
Total Time
Idle Time
1
-Select-a, b, db, e, cc, a, dItem 1
2
-Select-e, g, c, ha, d, fb, e, fItem 4
3
-Select-f, i, jg, i, jg, h, jItem 7
4
-Select-ki, kh, kItem 10
Total
What is the assembly-line efficiency? Round your answer to one decimal place.
%
Fill in the table below for a shift output of 24 pieces. Break ties by choosing the lowest task number. If your answer is zero, enter "0". Round your answers to the nearest whole number.
Workstation
Tasks
Total Time
Idle Time
1
-Select-a, b, e, ca, b, c, db, c, f, eItem 16
2
-Select-f, d, g, if, e, g, ia, d, g, iItem 19
3
-Select-h, j, kk, h, jh, kItem 22
Total
What is the assembly-line efficiency? Round your answer to one decimal place_______%
Answer & Explanation
Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!