Below are the data for a Time-Cost CPM Scheduling modelanalysis. The time is in days and the costs include both direct andindirect costs. If you crash this project to reduce the total timeby two days what is the total time of the project and total cost?Explain. (Note: Cut and paste your Precedence diagram.)
Activity | Immediate Predecessor | Normal Time | Crash Time | Normal Cost | Crash Cost |
A | None | 3 | 2 | 200 | 400 |
B | A | 4 | 3 | 300 | 600 |
C | A | 1 | --- | 400 | --- |
D | B and C | 3 | 2 | 200 | 250 |
E | D | 2 | 1 | 500 | 600 |
F | E | 2 | --- | 600 | --- |
G | E | 3 | 1 | 300 | 450 |
H | G | 1 | --- | 400 | --- |