Birmingham Bowling Ball Company (BBBC) uses a job-order costing
system to accumulate manufacturing costs. The company’s
work-in-process...
50.1K
Verified Solution
Link Copied!
Question
Accounting
Birmingham Bowling Ball Company (BBBC) uses a job-order costingsystem to accumulate manufacturing costs. The company’swork-in-process on December 31, 20x3, consisted of one job (no.3088), which was carried on the year-end balance sheet at $156,800.There was no finished-goods inventory on this date.
     BBBC applies manufacturingoverhead to production on the basis of direct-labor cost. (Thebudgeted direct-labor cost is the company’s practical capacity, interms of direct-labor hours, multiplied by the budgeteddirect-labor rate.) Budgeted totals for 20x4 for direct labor andmanufacturing overhead are $4,200,000 and $5,460,000 respectively.Actual results for the year follow.
  Direct materialused..................
$
5,500,000
  Directlabor......................
4,350,000
  Indirect materialused.................
63,000
  Indirectlabor.....................
2,860,000
  Factorydepreciation....................
1,740,000
  Factoryinsurance.....................
59,000
  Factoryutilities....................
832,000
  Selling andadministrative expenses
2,160,000
     Total
$
17,564,000
Job no. 3088 was completed in January 20x4; there was no work inprocess at year-end. All jobs produced during 20x4 were sold withthe exception of job no. 3154, which contained direct-materialcosts of $155,000 and direct-labor charges of $85,000. BBBC chargesany under- or overapplied overhead to Cost of Goods Sold.
4.
Prepare the journal entry needed to record the year’s completedproduction. (If no entry is required for atransaction/event, select "No journal entry required" in the firstaccount field.)
5-a.
Compute the amount of under- or overapplied overhead atyear-end.
5-b.
Prepare the necessary journal entry to record its disposition.(If no entry is required for a transaction/event, select"No journal entry required" in the first accountfield.)
Determine BBBC’s 20x4 cost of goods sold.
Finished Goods Jan 1
?
?
Cost of Goods Available for Sale
?
?
Unadjusted Cost of Goods Sold
?
?
Cost of Goods Sold
 Â
Answer & Explanation
Solved by verified expert
3.6 Ratings (336 Votes)
Solution 4 Predetermined overhead rate Budgeted overhead Budgeted direct labor cost 5460000 4200000 130 of direct labor cost Schedule of cost of completed production Birmingham Bowling Ball Company Particulars Amount Direct materials 550000000 Direct
See Answer
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Zin AI - Your personal assistant for all your inquiries!