Calculate the payback period of project S considering the following estimated data: Initial cost at...
80.2K
Verified Solution
Link Copied!
Question
Finance
Calculate the payback period of project S considering the following estimated data: Initial cost at time 0 = $1,000. After-tax, end of year cash inflows are as follows: first year $500; second year: $400; third year: $300; fourth year: $100. The risk-adjusted cost of capital (or WACC) is 10%. Select one: O a. 3.30 O b. 2.33 c. 2.80 d. 2.70