Schedule of Raw material to be purchased in May
|
|
May
|
(A)
|
Units to be Produced
|
3530
|
Units
|
(B)
|
Material Required per Unit
|
3
|
Ounces
|
(C=(A*B))
|
Total Material Required for Production
|
10590
|
Ounces
|
(D)
|
Add: Desired Closing Raw material Inventory
|
3069
|
Ounces
|
(E=(C+D))
|
Raw material Needed
|
13659
|
Ounces
|
(F)
|
Less: Opening Inventory Available
|
3177
|
Ounces
|
(G=(E-F))
|
Raw material to be purchased
|
10482
|
Ounces
|
Working Note
|
|
April
|
May
|
June
|
(A)
|
Units to be Produced
|
3210
|
3530
|
3410
|
(B)
|
Material Required per Unit (Ounces)
|
3
|
3
|
3
|
(C=(A*B))
|
Total Material Required
|
9630
|
10590
|
10230
|
(D)
|
Add: Desired Closing Raw material Inventory
|
3177*
|
3069**
|
|
(E=(C+D))
|
Total Raw material Needed
|
12807
|
13659
|
|
(F)
|
Less: Opening Inventory Available
|
3177
|
3177
|
3069
|
(G=(E-F))
|
Raw material to be purchased
|
9630
|
10482
|
|
Data for June is Incomplete as no details about ending raw
material was given in the question.
*(10590x30%)
**(10230x30%)