Christmas Express makes wreaths in batch sizes of 19. The cutting and assembly...
80.2K
Verified Solution
Link Copied!
Question
Accounting
Christmas Express makes wreaths in batch sizes of The cutting and assembly process takes minutes per wreath, and the decorating process time is minutes per wreath. It takes minutes to move the wreaths from the cutting and assembly process to the decorating process.
a Compute the valueadded, nonvalueadded, and total lead times of the wreath process.
Valueadded lead time minutes
Nonvalueadded lead time:
Move time
Withinbatch wait time
Total lead time minutes
b Compute the valueadded ratio. Round to one decimal place.
Answer & Explanation
Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!