Codelfa contracted with the State Rail Authority to excavatetunnels to do the concrete work on the construction of Sydney’sEastern Suburbs Railway. Various stages of the work were to becompleted by certain dates, and the whole contract was to becompleted within 130 weeks. Due to building noise, local residentsapplied for and were granted Injunctions to restrain work duringthe night, and as a result, Codelfa could not complete the contracton time.
Required: 1. Can a Term be implied into a contract to requirethe State Rail Authority to give an extension of time?
2. Discuss the legal condition of the Performance of thecontract.