Company uses job-order costing to estimate their costs and also set their prices. The following information is available:
Estimated total budgeted overhead $300,000
Estimated total budgeted machine hours 10,000
Estimated total budgeted direct labor hours 20,000
Estimated budgeted direct labor costs $75,000
is bidding on a job and has the following estimated information for that specific job:
Direct Materials Needed $9,000
Direct Labor Costs Needed $1,000
Direct Labor Hours Needed 225
Machine Hours Needed 100
The company uses machine hours to allocate overhead.,
Required
Calculate the following amounts:
Questions | Answers |
Calculate the overhead rate | |
Calculate the amount of overhead costs allocated to this specific job | |
Calculate the total costs of this specific job | |
Calculate the selling price of the specific job assuming that Porter adds 10% to the total cost of the job | |