Question
Accounting
Consider the following network with tasks duration in days:
(Note: Task N is a dummy task. It must be included in the relationships but its duration is 0. Be sure its duration is set to 0))
Task
Pessimistic
Likely
Optimistic
Fixed Cost
A
7
5
3
1000
B
3
2
1
600
C
12
7
2
2100
D
12
6
6
1800
E
9
8
7
800
F
24
12
6
2400
G
11
4
3
800
H
7
6
5
1200
I
6
4
2
1600
J
25
17
9
4200
K
7
5
3
3600
L
7
7
7
2100
M
12
10
8
3000
N
-
-
-
-
Project start on Monday 10/31/16. Thursday 11/24/16, Friday 11/25/16, 12/26/16, and 1/2/17 are holidays.
Determine critical path and its duration. When the project will end (date)?
There is a possibility that the starting task K may be delayed by 3 days. Will this impact the project completion date? If yes, when will be the new finish date? (After checking this out, please restore the project to its original schedule).
Assign the following resources to the tasks. All resources will be full time. (Set the leveling to manual first).
Task
Resource
Cost/day
A
R1
200
B
R2
300
C
R3
300
D
R4
300
E
R2
300
F
R4
300
G
R1
200
H
R5
200
I
R6
400
J
R5
200
K
R1
200
L
R3
300
M
R2
300
N
-
-
Check for over-allocation. Which resources are over allocated?
Level if necessary. Then determine the new critical path and duration.
What is the total cost of the project (Fixed+Resource cost)? How much does the project need in the first, second, and third weeks?
(Hint: Use Reports, cost, cash flow to find out weekly budget requirements)
After completing the assignment, please enter your answers in the attached answer sheet, and submit your answer sheet and your MPP file to the designated area in Moodle.
Answer Sheet
Answers:
Questions
Answers
Question 2. (2)
Critical Path:
Duration:
Finish date:
Question 4. (1)
Impact of 3 days delay in starting task K:
New finish date:
Question 6. (2)
Over allocated resources:
Question 7. (1)
Is leveling necessary?
New critical path:
Duration:
Question 8. (1)
Total project cost:
$
Total cash required for week 1:
$
Total cash required for week 2:
$
Total cash required for week 3:
$
2 10 6
Answer & Explanation
Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!