Create a schedule for the following data that starts June1st 2016. Assume that one can work 7 days a week and 30days a month.
Code | Description of Activity | Immediate Precedence | Duration (days) |
1 | Strategic plan phase | | 50 |
| | | |
2. | Team formation | | 70 |
3 | Master facility plan | 1,2 | 200 |
4. | Space programming | Finish with 3 | 240 |
| | | |
| | | |
| | | |
| | | |
| | | |
| | | |
| | | |
| | | |
| | | |
| | | |
| | | | | |
a. Show a Gantt chart for the schedule. Make sure that the chartshows the time scale on quarterly basis.
b. Make sure that the chart shows the critical path. Create thechart and copy the chart into the word document (do not provideyour project management files)