Direct materials (30 Ibs. @ $4 per Ib.) $ 120.00 Direct labor (5...
80.2K
Verified Solution
Link Copied!
Question
Accounting
Direct materials (30 Ibs. @ $4 per Ib.)
$
120.00
Direct labor (5 hrs. @ $14 per hr.)
70.00
Factory overheadVariable (5 hrs. @ $8 per hr.)
40.00
Factory overheadFixed (5 hrs. @ $10 per hr.)
50.00
Total standard cost
$
280.00
The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 60,000 units per quarter. The following flexible budget information is available.
Operating Levels
70%
80%
90%
Production in units
42,000
48,000
54,000
Standard direct labor hours
210,000
240,000
270,000
Budgeted overhead
Fixed factory overhead
$
2,400,000
$
2,400,000
$
2,400,000
Variable factory overhead
$
1,680,000
$
1,920,000
$
2,160,000
During the current quarter, the company operated at 90% of capacity and produced 54,000 units of product; actual direct labor totaled 265,000 hours. Units produced were assigned the following standard costs.
Direct materials (1,620,000 Ibs. @ $4 per Ib.)
$
6,480,000
Direct labor (270,000 hrs. @ $14 per hr.)
3,780,000
Factory overhead (270,000 hrs. @ $18 per hr.)
4,860,000
Total standard cost
$
15,120,000
Actual costs incurred during the current quarter follow.
Direct materials (1,615,000 Ibs. @ $4.10 per lb.)
$
6,621,500
Direct labor (265,000 hrs. @ $13.75 per hr.)
3,643,750
Fixed factory overhead costs
2,350,000
Variable factory overhead costs
2,200,000
Total actual costs
$
14,815,250
Problem 08-5AA Expanded overhead variances LO P5
(a) Compute the variable overhead spending and efficiency variances. (b) Compute the fixed overhead spending and volume variances. (c) Compute the total overhead controllable variance.
Actual Variable OH Cost
-1
Flexible Budget
-1
Standard Cost (VOH applied)
Actual hours
x
Actual variable rate
Actual hours
x
Standard variable rate
Standard hours
x
Standard variable rate
265,000
x
265,000
x
$8.00
270,000
x
$8.00
$2,120,000
$2,160,000
2
$40,000
-1
Variable overhead spending variance
$0
Unfavorable
Variable overhead efficiency variance
40,000
Favorable
Total variable overhead variance
Unfavorable
Actual Fixed OH Cost
-1
Budgeted Overhead
-1
Standard Cost (FOH applied)
Actual hours
x
Actual fixed rate
Standard hours
x
Standard fixed rate
265,000
x
270,000
x
$10.00
$2,700,000
2
-1
$0
0
Overhead Controllable Variance
Fixed overhead spending variance
Variable overhead efficiency variance
Variable overhead spending variance
Total overhead controllable variance
Answer & Explanation
Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!