During 2020, Sheridan Company started a construction job with a contract price of $1,376,000. The job was completed in 2022. The following information is available. The contract is non-cancellable.
2020
2021
2022
Costs incurred to date
$344,000
$709,500
$920,200
Estimated costs to complete
516,000
236,500
0
Billings to date (non-refundable)
258,000
774,000
1,376,000
Collections to date
232,200
696,600
1,225,500
Calculate the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. (Enter negative amounts using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45).)
2020
2021
2022
Gross profit / (loss)
$enter a dollar amount
$enter a dollar amount
$enter a dollar amount
Answer & Explanation
Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!