During the first quarter of 2022, Cullumber Company reports the following: Estimated overhead $221.260 Actual overhead $220.280. Estimated labour costs $170.204. Actual labour costs $172.500. The company allocates its overhead on the basis of direct labour cost. Calculate the predetermined overhead rate. Calculate the over-applied or under-applied manufacturing overhead