Entries and Schedules for Unfinished Jobs and Completed Jobs Tybee Industries Inc. uses a job...
50.1K
Verified Solution
Link Copied!
Question
Accounting
Entries and Schedules for Unfinished Jobs and Completed Jobs
Tybee Industries Inc. uses a job order cost system. The following data summarize the operations related to production for January, the first month of operations:
Materials purchased on account, $1,870.
Materials requisitioned and factory labor used:
Job
Materials
Factory Labor
301
$2,300
$2,400
302
2,810
3,240
303
1,860
1,580
304
6,300
5,950
305
4,000
4,540
306
2,920
2,880
For general factory use
780
3,550
Factory overhead costs incurred on account, $4,390.
Depreciation of machinery and equipment, $1,700.
The factory overhead rate is $40 per machine hour. Machine hours used:
Job
Machine Hours
301
36
302
15
303
42
304
74
305
38
306
41
Total
246
Jobs completed: 301, 302, 303, and 305.
Jobs were shipped and customers were billed as follows: Job 301, $7,370; Job 302, $7,980; Job 303, $14,850.
Required:
1. Journalize the entries to record the summarized operations. For a compound transaction, if an amount box does not require an entry, leave it blank.
Entries
Description
Debit
Credit
a.
Materials
Accounts Payable
b.
Work in Process
Factory Overhead
c.
Factory Overhead
Accounts Payable
d.
Factory Overhead
Accumulated Depreciation-Machinery and Equipment
e.
Work in Process
Factory Overhead
f.
Finished Goods
Work in Process
g.
Accounts Receivable
Sales
Cost of Goods Sold
Finished Goods
2. Post the appropriate entries to T accounts for Work in Process and Finished Goods, using the identifying letters as transaction codes. Insert memo account balances as of the end of the month.
Work in Process
(b)
(f)
(e)
Bal.
Finished Goods
(f)
(g)
Bal.
3. Prepare a schedule of unfinished jobs to support the balance in the work in process account.
Tybee Industries Inc. Schedule of Unfinished Jobs
Job
Direct Materials
Direct Labor
Factory Overhead
Total
No. 304
$
$
$
$
No. 306
Balance of Work in Process, January 30
$
4. Prepare a schedule of completed jobs on hand to support the balance in the finished goods account.
Tybee Industries Inc. Schedule of Completed Jobs
Job
Direct Materials
Direct Labor
Factory Overhead
Total
Finished Goods, January 30 (Job 305)
$
$
Answer & Explanation
Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!