Five jobs are ready for processing at time zero through a workstation. The details regarding...
60.1K
Verified Solution
Link Copied!
Question
Accounting
Five jobs are ready for processing at time zero through a workstation. The details regarding the processing time and the due date of completion are provided in the following table.
Job
Processing Time (days)
Days Due from Today
A
11
35
B
10
39
C
7
34
D
8
42
E
12
40
Using the shortest processing time (SPT) rule, it can be concluded that the average tardiness for the five jobs is:
a. more than 1.2 but less than or equal to 1.5 days.
b. more than 1.5 but less than or equal to 1.7 days.
c. more than 1.7 but less than or equal to 1.9 days.
d. more than 1.9 but less than or equal to 2.1 days.
Answer & Explanation
Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!