Given the following information, calculate the CV, SV, CPI, and SPI for this project. Also...
80.2K
Verified Solution
Link Copied!
Question
Accounting
Given the following information, calculate the CV, SV, CPI, and SPI for this project. Also provide recommendations to improve the projects performance if needed.
Activity A: This activity is complete. It was completed in 6 weeks; it was supposed to be completed in 5 weeks. The original budget for this activity was $400,000; in the end, it cost $450,000. Activity B: This activity is 50% complete. Its original budget was $100,000. The costs to date are $55,000. The original project plan had this activity scheduled for 5 weeks; currently it is entering its third week. Activity C: This activity is 75% complete. Its costs so far are $100,000. It is entering Week 4 of 5. It was planned to cost $100,000 when completed. Activity D: This activity is not started yet; it will start in 2 weeks. It is planned to cost $400,000. Its costs to date are $0
Answer & Explanation
Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!