Greenwood Company manufactures two products15,000 units of Product Y and 7,000 units of Product Z....
70.2K
Verified Solution
Link Copied!
Question
Accounting
Greenwood Company manufactures two products15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z:
Activity Cost Pool
Activity Measure
Estimated Overhead Cost
Expected Activity
Machining
Machine-hours
$
216,700
11,000
MHs
Machine setups
Number of setups
$
79,900
170
setups
Production design
Number of products
$
81,000
2
products
General factory
Direct labor-hours
$
247,000
10,000
DLHs
Activity Measure
Product Y
Product Z
Machining
6,700
4,300
Number of setups
60
110
Number of products
1
1
Direct labor-hours
7,700
2,300
1.What is the companys plantwide overhead rate? (Round your answer to 2 decimal places.) 2.Using the plantwide overhead rate, how much manufacturing overhead cost is allocated to Product Y and Product Z? (Round your intermediate calculations to 2 decimal places and final answers to the nearest dollar amount.)3. What is the activity rate for the Machining activity cost pool? (Round your answer to 2 decimal places.) 4. What is the activity rate for the Machine Setups activity cost pool? (Round your answer to 2 decimal places.) 5.What is the activity rate for the Product Design activity cost pool? (Round your answer to 2 decimal places.) 6. What is the activity rate for the General Factory activity cost pool? (Round your answer to 2 decimal places.)
7. Which of the four activities is a batch-level activity?
Machining activity
General factory activity
Product design activity
Machine setups activity
8.Which of the four activities is a product-level activity?
Machining activity
Product design activity
Machine setups activity
General factory activity
9.Using the ABC system, how much total manufacturing overhead cost would be assigned to Product Y? (Round your intermediate calculations to 2 decimal places and final answer to the nearest dollar amount.) 10. Using the ABC system, how much total manufacturing overhead cost would be assigned to Product Z? (Round your intermediate calculations to 2 decimal places and final answer to the nearest dollar amount.) 11. Using the plantwide overhead rate, what percentage of the total overhead cost is allocated to Product Y and Product Z? (Round your answers to 2 decimal places.) 12. Using the ABC system, what percentage of the Machining costs is assigned to Product Y and Product Z? (Round your answers to 2 decimal places.) 13.Using the ABC system, what percentage of Machine Setups cost is assigned to Product Y and Product Z? (Round your answers to 2 decimal places.) 14. Using the ABC system, what percentage of the Product Design cost is assigned to Product Y and Product Z? (Round your answers to 2 decimal places.) 15. Using the ABC system, what percentage of the General Factory cost is assigned to Product Y and Product Z? (Round your answers to 2 decimal places.)
Answer & Explanation
Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!