Holbrook, Inc., has identified the following overhead costs and cost drivers for next year:
Overhead Item | Expected Cost | Cost Driver | Expected Quantity |
Setup costs | $960,000 | Number of setups | 4,800 setups |
Ordering costs | $160,000 | Number of orders | 20,000 orders |
Maintenance | $640,000 | Machine hours | 64,000 MHs |
Power | $80,000 | Kilowatt hours | 200,000 kw hrs. |
The following are two of the jobs completed during the year:
| Job 701 | Job 702 |
Prime costs | $25,000 | $18,000 |
Units completed | 650 | 500 |
Direct labour hours | 180 | 220 |
Number of setups | 12 | 15 |
Number of orders | 16 | 30 |
Machine hours | 360 | 300 |
Kilowatt hours | 180 | 650 |
The companys normal activity is 40,000 direct labour hours.
Required
- Determine the unit cost of each job using direct labours to apply overhead
- Determine the unit cost for each job using Activity-based costing system (round off amounts to two decimal places.)