Transcribed Image Text
Huang Industries is considering a proposed project whoseestimated NPV is $12 million. This estimate assumes that economicconditions will be "average." However, the CFO realizes thatconditions could be better or worse, so she performed a scenarioanalysis and obtained these results:EconomicScenarioProbability ofOutcomeNPVRecession0.05($68 million)Below average0.20(14 million)Average0.5012 millionAbove average0.2018 millionBoom0.0530 millionCalculate theproject's expected NPV, standard deviation, and coefficient ofvariation. Round your answers to two decimal places. Enter youranswers for the project's expected NPV and standard deviation inmillions. For example, an answer of $13,000,000 should be enteredas 13.E(NPV)=?NPV=CV=