If a project has cash flows that alternate from negative to positive to negative again, the main concern in that situation would be:
A. the possibility that the NPV estimate will not take into account the time value of money
B. that the cash flow estimates are incorrect B. that networking capital needs are not being met
C. the possibility of multiple IRRs
D. that the IRR will be negative
Answer & Explanation
Solved by verified expert