In February 2023, Crane Construction signed a contract and commenced construction on a parking garage....

70.2K

Verified Solution

Question

Accounting

In February 2023, Crane Construction signed a contract and commenced construction on a parking garage. The total contract price
was $89.80 million and was expected to be completed in July 2027 at a total estimated cost of $82.0 million. Payment by the customer
was to be made in several stages, based on significant events and dates throughout the construction timeline. The customer was to
have control over the parking garage and was able to make major changes to the project during the construction process. Crane's year-
end was September 30.
By the end of September, 2023, Crane had incurred $20,500,000 in costs and had invoiced $10,600,000 in progress billings.
$7,800,000 of the progress billings had been collected.
By September 30,2024, Crane had incurred $43,450,000 in total costs and had invoiced $45,003,000 in progress billings, including
the progress billings in 2023. Of the total billings, $30,000,000 in total had been collected. Also, Crane reviewed its cost estimates on
the project, and now believed the parking garage would cost $79.00 million in total to complete.
(a)
No. Account Titles and Explanation
Materials, Cash, Payables
(To record the 2023 cost of construction)
Billings on Construction in Process
(To record the 2023 progress billings)
In February 2023, Crane Construction signed a contract and commenced construction on a parking garage. The total contract price
was $89.80 million and was expected to be completed in July 2027 at a total estimated cost of $82.0 million. Payment by the customer
was to be made in several stages, based on significant events and dates throughout the construction timeline. The customer was to
have control over the parking garage and was able to make major changes to the project during the construction process. Crane's year-
end was September 30.
By the end of September, 2023, Crane had incurred $20,500,000 in costs and had invoiced $10,600,000 in progress billings.
$7,800,000 of the progress billings had been collected.
By September 30,2024, Crane had incurred $43,450,000 in total costs and had invoiced $45,003,000 in progress billings, including
the progress billings in 2023. Of the total billings, $30,000,000 in total had been collected. Also, Crane reviewed its cost estimates on
the project, and now believed the parking garage would cost $79.00 million in total to complete.
(a)
No. Account Titles and Explanation
Debit
Credit
(To record the 2023 cost of construction)
10,600,000
Billings on Construction in Process
(To record the 2023 progress billings)
7,800,000
(To record the 2023 cash collections)
Billings on Construction in Process
Revenue from Long-Term Contracts
(To record the 2023 revenue)
(To record the 2023 construction expenses)
image

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students