In February Crane Construction signed a contract and commenced construction on a parking garage. The total contract price
was $ million and was expected to be completed in July at a total estimated cost of $ million. Payment by the customer
was to be made in several stages, based on significant events and dates throughout the construction timeline. The customer was to
have control over the parking garage and was able to make major changes to the project during the construction process. Crane's year
end was September
By the end of September, Crane had incurred $ in costs and had invoiced $ in progress billings.
$ of the progress billings had been collected.
By September Crane had incurred $ in total costs and had invoiced $ in progress billings, including
the progress billings in Of the total billings, $ in total had been collected. Also, Crane reviewed its cost estimates on
the project, and now believed the parking garage would cost $ million in total to complete.
a
No Account Titles and Explanation
Materials, Cash, Payables
To record the cost of construction
Billings on Construction in Process
To record the progress billings
In February Crane Construction signed a contract and commenced construction on a parking garage. The total contract price
was $ million and was expected to be completed in July at a total estimated cost of $ million. Payment by the customer
was to be made in several stages, based on significant events and dates throughout the construction timeline. The customer was to
have control over the parking garage and was able to make major changes to the project during the construction process. Crane's year
end was September
By the end of September, Crane had incurred $ in costs and had invoiced $ in progress billings.
$ of the progress billings had been collected.
By September Crane had incurred $ in total costs and had invoiced $ in progress billings, including
the progress billings in Of the total billings, $ in total had been collected. Also, Crane reviewed its cost estimates on
the project, and now believed the parking garage would cost $ million in total to complete.
a
No Account Titles and Explanation
Debit
Credit
To record the cost of construction
Billings on Construction in Process
To record the progress billings
To record the cash collections
Billings on Construction in Process
Revenue from LongTerm Contracts
To record the revenue
To record the construction expenses