Indiana Co. began a construction project in 2018 with a contract price of $162 million...
90.2K
Verified Solution
Link Copied!
Question
Accounting
Indiana Co. began a construction project in 2018 with a contract price of $162 million to be received when the project is completed in 2020. During 2018, Indiana incurred $39 million of costs and estimates an additional $85 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. In 2019, Indiana incurred additional costs of $59 million and estimated an additional $40 million in costs to complete the project. Indiana (Do not round your percentage calculated)
Answer & Explanation
Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!