It is desired to take advantage of the current of a river comingupstream for an electric power generation project. The point wherethe turbine-generator will be installed is 50 meters below theupstream level. The upstream speed is 9 m / s and the downstreamspeed is 2 m / s. There will be a mass flow of water of 1500 kg /s. Calculate an estimate for the generation of electrical powerproduced if you have a turbine with an efficiency of 0.93 and anelectric generator with an efficiency of 0.95.