During March, Aragon Company worked on three jobs. Data relating to these three jobs follow:
Job 78
Job 79
Job 80
Units in each order
110
160
290
Units sold
160
Materials requisitioned
$770
$720
$3,161
Direct labor hours
121
176
493
Direct labor cost
$1,573
$2,816
$4,141
Overhead is assigned on the basis of direct labor hours at a rate of $7.60 per direct labor hour. During March, Jobs 78 and 79 were completed and transferred to Finished Goods Inventory. Job 79 was sold by the end of the month. Job 80 was the only unfinished job at the end of the month.
1. Calculate the per-unit cost of Jobs 78 and 79. Round your answers to the nearest cent.
Job 78
$___ per unit
Job 79
$___ per unit
2. Compute the ending balance in the work-in-process inventory account. Round your answer to the nearest cent.
$____
Feedback
3. Prepare the journal entries reflecting the completion of Jobs 78 and 79 and the sale of Job 79. The selling price is 120 percent of cost. Round your answers to the nearest cent.
Completion of Jobs 78 & 79
Finished Goods
___
Work in Process
____
Sale of Job 79 (cost)
Cost of Goods Sold
____
Finished Goods
_____
Sale of Job 79 (sale)
Accounts Receivable or Cash
____
Sales Revenue
____
Answer & Explanation
Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!