Job Costs Using Activity-Based Costing Reider Company is a job-order costing firm that uses activity-based...
60.1K
Verified Solution
Link Copied!
Question
Accounting
Job Costs Using Activity-Based Costing
Reider Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Reider identified three overhead activities and related drivers. Budgeted information for the year is as follows:
Activity
Cost
Driver
Amount of Driver
Materials handling
$112,500
Number of moves
5,000
Engineering
97,500
Number of change orders
6,500
Other overhead
196,800
Direct labor hours
48,000
Reider worked on four jobs in July. Data are as follows:
Job 13-43
Job 13-44
Job 13-45
Job 13-46
Beginning balance
$22,700
$18,300
$4,100
$0
Direct materials
$5,600
$9,150
$12,900
$11,600
Direct labor cost
$810
$1,050
$1,600
$150
Number of moves
42
52
29
4
Number of change orders
29
41
24
19
Direct labor hours
810
1,050
1,600
150
By July 31, Jobs 13-43 and 13-44 were completed and sold. Jobs 13-45 and 13-46 were still in process.
3. Calculate the balance in Work in Process on July 31. $fill in the blank dc82740c307302a_1
4. Calculate the cost of goods sold for July. $fill in the blank dc82740c307302a_2
5. What if Job 13-46 required no engineering change orders? What is the difference in the new cost of Job 13-46?
$
Answer & Explanation
Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!