Job | Order | Days Waiting | Process Time | Due Date | Start | Finish | Flow Time | Late |
Allison | first | 6 | 2 | 14 | | | | |
Miller | second | 4 | 8 | 69 | | | | |
Noel | third | 2 | 12 | 33 | | | | |
Dickson | fourth | 3 | 13 | 47 | | | | |
Cheng | fifth | 5 | 15 | 12 | | | | |
Bahouth | sixth | 1 | 16 | 88 | | | | |
Hepner | seventh | 7 | 17 | 20 | | | | |
A. If these jobs have already been sequenced what method was used?
[ Select ] ["Earliest Due Date (EDD)", "Slack Time Remaining (STR)", "Shortest Processing Time (SPT)", "First-come, First-served (FCFS)"]
B. Using this sequence Calculate the Average Days Past Due.
[ Select ] ["34.4", "24.4", "14.4", "54.4"]
C. Using this sequence Calculate the Average Flow Rate.
[ Select ] ["32.3", "22.3", "12.3", "42.3"]