Correct Answer ----Predetermined overhead rate -$2.50
Explanation and calculations
Schedule of Predetermined Overhead
rate
|
Manufacturing Overheads
|
|
Rent of Factory Building
|
$ 15,000.00
|
Depreciation on Factory Equipment
|
$ 8,000.00
|
Indirect Labor
|
$ 12,000.00
|
Production Supervisor's Salary
|
$ 15,000.00
|
(A) Total Estimated Overheads
|
$ 50,000.00
|
(B) Total Direct labor hours in the year
|
$ 20,000.00
|
(A/B) Predetermined Overhead Rate per labor hour
|
$
2.50
|
Sales salary is a selling expense and not a product cost hence
it will not be included for calculating predetermined overhead
rate.
Direct material and labor are direct expenses, they are product
cost but not a part of Overhead cost.