KPNG Consulting has five projects to consider. Each will requiretime in the next four quarters according to the table below
Project | Time in 1st quarter | Time in 2nd quarter | Time in 3rd quarter | Time in 4th quarter | Revenue $k |
A | 6 | 9 | 3 | 1 | 240 |
B | 4 | 13 | 6 | 4 | 120 |
C | 8 | 0 | 8 | 6 | 150 |
D | 3 | 3 | 1 | 7 | 60 |
E | 12 | 3 | 4 | 9 | 250 |
Revenue from each project is also shown. Develop a model whosesolution would maximize revenue, meet the time budget of: 28 in the1st quarter, 20 in the 2nd quarter, 18 in the 3rd quarter and 16 inthe 4th quarter; at least three projects; and not do both projectsC and D. If project B is chosen, project D must be chosen.