Make some assessments of the maintenance scheduling of a ship. Use PERT three-estimate approach. You...
90.2K
Verified Solution
Link Copied!
Question
Accounting
Make some assessments of the maintenance scheduling of a ship. Use PERT three-estimate approach. You are to identify slack and critical activities in the schedule using the PERT mean time. Further, you are to determine the date and time to enter the dry-dock so that with a 80 % probability, the vessel can be finished with the maintenance by the 15th of April 2022 at 12:00 UTC. Make necessary assumptions. You should make use of Excel to do the estimates.
Below are the activities that are mapped out for the maintenance to be done on the ship.
Activity
Immediate predecessor
Optimistic estimate
Most likely estimate
Pessimistic estimate
A
-----
1
1
3
B
A
1
2
3
C
B
3
4
6
D
B
1
2
3
E
B
2
3,5
8
F
C
1
1
1
G
C
1
1
2
H
C
3
3
4
I
F
1
2
3
J
F
1
3
6
K
G
1
3
4
L
G
3
5
7
M
G
1
2
3
N
H
3
4
6
O
DE
2
4
5
P
D
3
5
6
Q
I
2
3
5
R
IJK
3
3
4
S
L
2
3
4
T
L
3
3
6
U
N
2
5
9
V
N
2
4
7
W
OP
3
5
8
X
Q
4
5
7
Y
RST
1
2
3
Z
MUV
3
4
6
*a
W
2
2
3
*b
W
1
3
4
*c
OXYZ
1
2
3
*d
*a *b
2
3
5
*e
*c
2
3
4
The activities noted *a, *b are not special activities, and are to be considered as the other activities.
Answer & Explanation
Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!